Skip to content
Author
UPDATED:

LAKEPORT — The Lake County Board of Supervisors (BOS) authorized change orders for the Middletown Senior Center and Library project. Nine items were covered in the change order including a time extension and a funding increase.

Eric Seely, deputy county administrative officer, presented the change orders to the BOS. Changes include a six-day time extension because of weather, five charges for additional work and materials and three credits for reimbursements and deletions.

Additional work and materials include power circuits for automatic door openers, lumber for skylights, electrical outlet for service vehicles, relocation of plumbing and additional insulation.

Credits were applied for the county”s reimbursement of the purchase a KNOX-BOX? rapid entry system, cast iron drainage pipe that was changed to PVC piping and deletion of conduits and receptacles.

Funding was increased by $3,232. Seely said sufficient funds are available in the project budget to cover the additional expenses.

The BOS also authorized an amendment to an agreement with Kappe + Du Architects, for which Seely said funding is available in the uncommitted portion of the project budget.

Seely said the original agreement with the company was in the amount of $248,360. The agreement had a limited construction phase budget and is approaching the end of the funds allocated for construction support.

Seely said although efforts were made to reduce the need for architect services, Kappe + Du responded to more than 130 Requests for Information and more than 35 submittals from the contractor, R.E. West. The architectural firm has also provided comments on two change order requests from subcontractor, Bay Manufacturer, Inc.

“This has required considerably more effort than was anticipated when the original agreement was negotiated,” Seely said. “As a result, the hours of service provided for in the agreement have been exhausted.”

Amendment to the agreement provides for up to 24 hours per month of additional services from June to December at a reduced hourly rate, with a ceiling of $25,000. If the project is completed prior to December, Seely said the total additional cost may be less. “Now that we have completed the initial phases of the project, the construction contractors” Requests for Information and submittals will be much less in the months ahead and no additional engineering should be required,” he said.

Seely said significant savings resulted because of his ability to assume many of the day-to-day construction management responsibilities that would otherwise be performed by the architect; however there are times when the architects” expertise is needed and cannot be substituted.

Originally Published:

RevContent Feed

Page was generated in 2.0857720375061